Wailoa Power station maintenance a success: Patel

06:36 Wed Dec 06, 2017


Taken from/By: FBC News
Report by: Rachael Nath

The Fiji Electricity Authority main valve replacement at Wailoa Power Station over the long weekend has been hailed a success.

Chief Executive, Hasmukh Patel says there were no hiccups during the replacement.

Patel adds an engineering team from Europe provided the FEA team with assistance during the maintenance work.

“We had a very tight program, we started at on Friday night at 10pm to make sure we are able to meet the demand of Viti Levu on a working day. The demand starts at 8am so we had to make sure the station was re-energized before 8am this morning and we successfully did that.”

Patel says a similar project will be undertaken during Easter next year.